The Avenida de Arjona collector works reach 40 percent

Topics Ayuntamiento de Jaén

The emergency works on the Avenida de Arjona in Jaén have installed 90 of the 226 meters of planned pipe and are moving toward resurfacing the road.

JaénYa newsroom ·

Una zanja profunda junto a una acera, con una excavadora y seis personas con chalecos reflectantes observando la obra.
Photo: Ayuntamiento de Jaén

The renovation of the collector on Avenida de Arjona in Jaén is progressing. Of the 226 metres of 1,200-millimetre-diameter PVC pipe planned, 90 linear metres have already been installed and covered, around 40 per cent of the section. The concreting of this part of the infrastructure is at 70 per cent.

The work is an emergency action and responds to the damage caused by the recent torrential rains, which exposed the collector's limitations in draining the accumulated volume of water. The fault also showed that there were still old galleries in poor condition from decades ago that caused leaks. The work is being carried out in coordination with Aqualia, the company that holds the water service concession, according to the Ayuntamiento.

Larger pipe and new discharge chamber

The project includes a large prefabricated concrete manhole, 2 by 2.5 metres, which will speed up the work and reduce risks during its execution. It also includes a final section with 1,500-millimetre-diameter concrete pipe and a new discharge chamber.

The work does not stop underground: afterwards the avenue's surface will be restored. Drainage and surface work are coordinated so as not to intervene twice on the same road.

The mayor of Jaén, Julio Millán, said during a technical visit that the intervention will make it possible to «renew and expand the existing infrastructure, notably increasing its capacity to drain rainwater and reducing the risk of future incidents». The visit was attended by the Government team councillors Francisco Lechuga, Javier Padorno and Carmen Elvira, together with Aqualia's manager in the city, Manuel Holguín, and part of the technical team.

The councillor for the Economic area, Francisco Lechuga, explained that this type of intervention is entrusted to the water concessionaire and that the action will continue with a second tender, a second phase that connects the current work with the Gran Eje and that will have funding from the EDIL Funds.

Share this story

Shall we let you know what matters?

Phone alerts

Change or remove it in my alerts

What it's about

Economy and employment